Temporary Fire Safety Arrangements During Building Renovations
Discover how to manage fire hazards, maintain safe escape routes, protect occupants and coordinate contractors while renovation work changes the fire safety conditions of a building.
At a glance: what should be in place?
Temporary fire safety arrangements are the interim controls used to protect people and property while construction, refurbishment or maintenance changes normal building conditions. They may include a revised fire risk assessment, protected escape routes, suitable temporary alarms, managed hot work, fire watch arrangements, controlled storage, and a formal process for managing impaired fire protection systems.
The arrangements must reflect the building, the work being undertaken, the people present and the actual condition of the premises. A generic checklist is useful, but it cannot replace a site-specific assessment by a competent person.
What Are Temporary Fire Safety Arrangements During Building Renovations?
Temporary fire safety arrangements during building renovations are the planned measures introduced to keep a building safe while normal fire precautions are altered, temporarily unavailable or exposed to additional hazards. Renovation work can affect escape routes, fire doors, alarm coverage, sprinkler protection, electrical installations, fire-resisting walls and the way people move around a workplace.
For example, an office refurbishment may require a corridor to be closed, a ceiling to be removed or a smoke detector to be isolated during dusty work. A hotel renovation might introduce contractors, temporary electrical supplies, combustible packaging and hot work while guests continue using other parts of the premises. Each situation requires controls based on the specific hazards and the people who could be affected.
Temporary arrangements are not simply signs placed around a work area. They form a coordinated safety plan covering fire prevention, early warning, safe evacuation, emergency response and the restoration of normal protection after work is complete.
Examples of temporary fire precautions
Preventing ignition
Authorising hot work, controlling temporary electrics, separating combustible materials from heat sources and enforcing suitable smoking restrictions.
Maintaining escape
Providing usable routes, clear directional signs, suitable lighting and alternative arrangements when the normal route is affected.
Maintaining warning
Ensuring people can receive and recognise a fire warning despite construction noise, temporary partitions or changes to detector coverage.
Managing impairment
Controlling planned outages of alarms, sprinklers or other protective systems, including authorisation, notifications and restoration checks.
Why Is Fire Safety More Challenging During Renovation Work?
Renovation projects introduce changing hazards into buildings that may already have established fire safety arrangements. The original emergency plan may no longer be suitable once a partition is removed, a corridor is closed or a fire alarm zone is isolated. The risk can change from one day to the next as contractors move between work areas and construction materials arrive on site.
The UK Health and Safety Executive advises those managing construction fire safety to identify fuel and ignition sources and provide appropriate arrangements for escape, warning and firefighting. In occupied buildings, particular attention is needed to prevent construction activities from interfering with existing escape routes, fire separation, alarms, dry risers or sprinklers. See the HSE guidance on general fire safety in construction.
Common fire hazards during refurbishment
- Hot work: welding, cutting, grinding, soldering and torch-applied processes can create sparks, heat or molten material.
- Combustible waste: packaging, timber offcuts, insulation, dust and removed fittings can provide fuel.
- Temporary electrics: damaged cables, overloaded circuits, unsuitable connections or poorly positioned equipment can create ignition hazards.
- Flammable products: adhesives, solvents, coatings and certain cleaning materials may produce flammable vapours.
- Altered escape routes: temporary barriers, stored equipment and work platforms can obstruct access to exits.
- Damaged fire separation: openings in walls, floors and ceilings can allow smoke and fire to spread between areas.
- Reduced detection: dust, temporary coverings, removed detectors or isolated zones can affect warning arrangements.
- Unfamiliar occupants: visiting workers may not know the building layout, alarm sound or assembly point.
The combination of these factors is especially important. A small ignition source may become more serious if combustible waste is nearby, a fire door has been removed and the alarm is not operating in the affected area. Fire safety planning must therefore examine how hazards interact rather than treating each item in isolation.
Who Is Responsible for Fire Safety During Building Renovations?
Responsibility depends on the premises, the jurisdiction, contractual arrangements and who has control over the building or work activity. In England, the Regulatory Reform (Fire Safety) Order 2005 establishes duties for the responsible person in relevant premises. The person controlling a construction site may also have important responsibilities for site fire precautions. Employers, building owners, occupiers, facilities managers and contractors may each have duties relating to the areas and activities under their control.
The UK government’s guidance on fire safety responsibilities explains the role of the responsible person and the need for coordination where responsibilities overlap. A contractor’s appointment does not automatically remove the building operator’s responsibilities for occupied areas.
Key responsibilities in practice
| Role | Typical responsibilities to agree |
|---|---|
| Building owner or occupier | Coordinate building-wide arrangements, share relevant information and ensure the fire risk assessment reflects changes. |
| Principal contractor or site manager | Manage construction hazards, site access, work sequencing, hot work controls and daily site conditions. |
| Facilities or fire safety manager | Coordinate alarm and sprinkler impairments, review escape routes and communicate changes to occupants. |
| Specialist fire system contractor | Carry out authorised work on relevant systems, record the scope of impairment and verify restoration. |
| Subcontractors and workers | Follow site rules, maintain housekeeping, report hazards and stop unsafe work in accordance with site procedures. |
| Responsible person or designated competent adviser | Ensure risks are assessed and suitable controls, emergency procedures and reviews are in place within their remit. |
Before work begins, document who can authorise changes, who can stop the work, who contacts the fire and rescue service and who decides whether the affected area can remain occupied. Include out-of-hours arrangements, because an alarm fault or unsecured work area may persist after the main contractor leaves.
For more information about the duties associated with workplace fire safety, read workplace fire safety responsibilities on this website.
Review the Fire Risk Assessment Before Work Starts
A fire risk assessment should be reviewed whenever planned renovation work could significantly affect existing hazards or precautions. The review should happen before the work begins, not after an escape route has been blocked or an alarm has been isolated.
The UK government’s five-step fire risk assessment checklist provides a useful framework: identify hazards, identify people at risk, evaluate and act, record and train, then review. Apply the process to the actual building and planned work rather than relying on a generic form.
What should the review examine?
- Scope of work: identify demolition, drilling, electrical work, ceiling removal, partition changes and hot work.
- People affected: consider employees, contractors, customers, residents, visitors and people who may need assistance to evacuate.
- Building layout: check exit locations, staircases, corridors, fire doors, compartment boundaries and assembly points.
- Fire protection: establish which detectors, alarms, sprinklers, extinguishers, emergency lights and other systems could be affected.
- Fuel and ignition: identify stored materials, waste, flammable liquids, temporary power and heat-producing activities.
- Emergency response: confirm warning methods, evacuation procedures, responsible contacts and arrangements for calling emergency services.
- Control measures: assign an owner and completion deadline to each action before work is authorised.
- Review triggers: define when a new assessment or review is required, such as a changed work area, new hazard or failed control.
The assessment should be proportionate to the complexity and risk of the project. A small decorating job in an unoccupied room may need fewer controls than a multi-storey refurbishment in an occupied healthcare facility. Where the building has complex evacuation arrangements or vulnerable occupants, competent specialist advice may be essential.
Maintain Safe Escape Routes and Fire Compartmentation
People must be able to recognise a warning and reach a place of safety using routes that remain usable during the renovation. The escape plan must reflect the building’s temporary layout, not only the finished design or the original floor plan.
Before closing a corridor, stairwell or exit, assess the impact on travel distances, available alternatives, access for people with disabilities and the evacuation strategy. Do not assume that a temporary sign makes an unsuitable escape route acceptable. Where an alternative route cannot provide adequate safety, the work or occupancy arrangements may need to change.
Practical escape-route controls
- Keep designated escape routes free of tools, waste, materials, cables and equipment.
- Use barriers and clear signs to distinguish closed construction areas from routes available to occupants.
- Provide suitable temporary lighting where normal lighting is affected or where the assessment identifies a need.
- Check that fire exits can be opened as intended and are not obstructed by deliveries, skips or temporary fencing.
- Maintain fire-resisting doors and partitions wherever they are needed to protect escape routes.
- Control temporary openings in compartment walls and floors, including penetrations for cables, pipes and services.
- Review arrangements for anyone who may need assistance, and communicate the revised evacuation plan to relevant staff.
- Inspect routes at the beginning of shifts and after deliveries, layout changes or major work activities.
Why fire doors and compartmentation matter
Fire-resisting construction helps limit the spread of fire and smoke. During refurbishment, a fire door may be removed for replacement, a wall may be opened for services, or a ceiling void may be exposed. These changes can undermine the protection assumed in the existing fire strategy.
Plan penetrations and temporary openings so that suitable fire-stopping or alternative protection is provided at the appropriate stage. Do not leave unprotected openings simply because the permanent installation will be completed later. Any temporary measure must be suitable for the hazard and agreed by the competent person responsible for the fire strategy.
Where a fire door is temporarily unavailable, do not wedge open another door or assume a temporary barrier provides equivalent protection. Assess the effect on the building and implement appropriate controls before continuing work.
Provide Effective Temporary Fire Detection and Warning
Construction noise, dust, temporary walls and changes to room layouts can affect fire detection and warning. The objective is to ensure that everyone who needs to respond can receive a clear warning in time to follow the emergency procedure.
The appropriate arrangement depends on the premises, fire strategy, occupancy, work activity and applicable requirements. Depending on the assessment, it may involve maintaining the existing system, adding suitable temporary detection or warning devices, changing the monitored areas, or introducing other authorised measures during a controlled impairment.
Managing detector coverings and dust
Dust-producing work can affect smoke detectors. Any covering or isolation must be managed under an agreed procedure by authorised personnel. A detector should not be covered indefinitely or left out of service after the dusty activity has finished. The relevant device or zone must be checked, cleaned where necessary and returned to service according to the system manufacturer’s instructions and the responsible person’s procedure.
Do not assume that removing one detector is harmless because others remain elsewhere in the building. The effect depends on the coverage, fire strategy, room configuration and the risk created by the work.
Make the warning recognisable
- Confirm that warning signals can be heard or otherwise perceived in the affected areas.
- Consider whether machinery, drilling, hearing protection or enclosed work zones could mask an alarm.
- Provide clear instructions for visitors and contractors who are unfamiliar with the building.
- Test temporary arrangements as required by the site procedure and system specifications.
- Explain who can raise the alarm and how the emergency services will be contacted.
Where an alarm or detection impairment affects occupied areas, a competent person should determine the necessary interim measures. If adequate warning cannot be maintained, restricting access or suspending affected activities may be necessary. A manual whistle, air horn or other temporary device should not be treated as a universal replacement for a required fire alarm system.
Control Hot Work and Other Ignition Sources
Hot work includes activities such as welding, flame cutting, grinding and certain soldering or torch-applied operations that can produce heat, sparks or molten material. These activities require particular care in buildings undergoing renovation because hidden combustible materials, dust, cavities and concealed voids may be exposed.
A formal hot-work permit system can help control higher-risk activities. A permit is a management tool, not a guarantee of safety. It should confirm that the work has been assessed, precautions are in place, responsible people are identified and the area will be checked at the required stages.
Hot-work precautions
- Consider alternatives. Where reasonably practicable, use a method that avoids flame, sparks or excessive heat.
- Inspect the work area. Identify combustible materials, openings, concealed spaces and any routes through which sparks could travel.
- Prepare the area. Remove or suitably protect combustible materials and ensure that the proposed work will not compromise escape routes or fire protection.
- Check nearby areas. Assess the other side of walls, floors and partitions where heat or sparks could cause ignition.
- Authorise the permit. Record the activity, location, precautions, start and finish times, responsible people and conditions requiring work to stop.
- Provide suitable firefighting equipment. Ensure it is appropriate for the hazards and that designated users are competent to use it.
- Monitor the work. Maintain the specified fire watch during the activity and carry out post-work monitoring for the period set by the risk assessment and site procedure.
- Close the permit properly. Check the work area, address any issues and record completion only when the required conditions have been met.
Control temporary electrical equipment and heating
Temporary power supplies, extension leads, lighting, battery charging and portable heaters should be suitable for the environment and used in accordance with competent advice and applicable electrical safety requirements. Protect cables from damage, avoid unsafe connections and prevent equipment from creating trip hazards or obstructing escape routes.
Keep heating equipment away from combustible materials and follow manufacturer instructions. Do not use improvised electrical arrangements or allow unapproved equipment into the work area. Report damaged cables, overheating, unusual smells or other signs of a potential fault promptly.
For additional contractor-focused guidance, link readers to fire safety for contractors.
Manage Combustible Materials, Waste and Flammable Products
Good housekeeping is a direct fire prevention measure. Packaging, timber, insulation offcuts, dust, discarded fittings and other waste can accumulate quickly during refurbishment. If these materials are allowed to build up near ignition sources or escape routes, they can increase the likelihood or consequences of a fire.
Establish clear rules for waste removal, material storage and end-of-shift inspections. Waste should be removed at a frequency that reflects the work and the amount of combustible material generated. Do not allow temporary storage to spread into corridors, stairwells, plant rooms or other areas where it could create a fire or evacuation hazard.
Storage and housekeeping controls
- Store materials only in designated areas agreed by site management.
- Keep combustible stock away from hot work, heaters, electrical equipment and other ignition sources.
- Keep flammable liquids in suitable, properly labelled containers and store them in accordance with the relevant safety information and site arrangements.
- Control quantities brought into the building so that unnecessary stocks do not accumulate.
- Remove waste regularly and use suitable containers and designated collection points.
- Keep plant rooms, electrical cupboards, stairways and fire equipment access clear.
- Control smoking and any designated smoking arrangements in accordance with site rules and applicable law.
- Secure the site against unauthorised access where this could introduce an arson or other fire risk.
Where flammable products are used, consult the product safety information and relevant workplace controls. Do not rely solely on a product label or a general statement that a material is safe. Storage, ventilation, ignition control and spill response must reflect the actual substance and conditions.
What If the Fire Alarm or Sprinkler System Must Be Switched Off?
Sometimes construction work requires an alarm zone, detector, sprinkler section or other fire protection system to be temporarily isolated. Such work should be planned and controlled. An impairment can leave people or parts of a building less protected than the original fire strategy intended.
Only authorised, competent personnel should operate or modify relevant systems in accordance with the building’s procedures. The person responsible for managing the impairment should understand the affected area, duration, reason, risks and interim precautions.
Use a formal impairment procedure
- Identify exactly which device, zone or system will be affected and why.
- Assess the effect on people, escape arrangements, adjacent areas and the overall fire strategy.
- Obtain approval from the designated authority before isolation.
- Notify the relevant building management team, occupants, monitoring provider and other parties identified in the site procedure.
- Introduce proportionate interim controls, which may include additional inspections, a trained fire watch, restrictions on hot work or limits on occupancy.
- Record the start time, affected area, responsible person and expected restoration time.
- Monitor the impairment and escalate any extension or change in conditions for reassessment and authorisation.
- Restore the system promptly when the work permits and arrange the required checks or tests.
- Confirm that the system is operational, close the impairment record and notify relevant parties.
Important safety principle
Do not leave an alarm or suppression system isolated simply because the contractor has finished the immediate task. Confirm that the system has been restored and that the affected equipment and coverage are suitable for service. If adequate fire protection cannot be maintained, the responsible person should assess whether the affected area must be restricted or vacated until suitable protection is restored.
Communicate Temporary Procedures to Workers and Occupants
A well-designed plan is ineffective if people do not know what has changed. Contractors may be unfamiliar with the premises, while existing employees may continue following an old route or assume a system is operating normally. Communication should take place before the change and whenever the arrangement is revised.
Information to communicate
- Which areas are under renovation and which areas remain open.
- Where to find the current escape routes and assembly point.
- How the fire warning will be raised and what it sounds or looks like.
- Who to contact about blocked routes, damaged fire doors, alarm faults or unsafe storage.
- Which activities require permission, including hot work and work affecting fire systems.
- What to do if a temporary barrier, alarm device or other precaution is damaged or unavailable.
- How people who need assistance will be supported under the evacuation arrangements.
Provide induction information to contractors and new workers before they begin relevant activities. Use language and formats that the intended audience can understand. Signage can reinforce instructions, but it should not be the only way critical safety information is communicated.
Fire drills or other exercises should be considered where appropriate to verify the revised arrangements. Coordinate them with building operations and the construction team so that they test the plan without introducing additional risks. After an exercise or real alarm, record lessons and correct any identified weaknesses.
Inspect, Review and Reinstate Fire Safety Measures
Temporary arrangements require active management. A route that was clear in the morning may be blocked by a delivery in the afternoon. A detector may be isolated for one task but remain isolated after the task finishes. A temporary partition may be moved without the evacuation plan being updated.
Set inspection frequency according to the risk, the pace of work and the conditions on site. Higher-risk activities or rapidly changing layouts may require more frequent checks than stable, low-risk work areas. The inspection schedule should identify who carries out each check, what must be examined and how defects are reported and resolved.
What should inspections cover?
- Escape routes, exit doors, signage and emergency lighting.
- Fire doors, temporary barriers, fire stopping and compartment boundaries.
- Fire alarm availability, any active impairment records and temporary warning arrangements.
- Access to extinguishers, fire points and other emergency equipment.
- Hot-work permits, fire watch records and completion checks.
- Combustible waste, material storage and temporary electrical equipment.
- Changes in occupancy, work location, shift patterns or building use.
- Completion of actions raised in earlier inspections and risk assessment reviews.
Handover when renovation work is complete
Completion of the physical work does not automatically mean that the building’s fire safety arrangements are ready for normal use. The final stage should confirm that temporary barriers and signs are removed when appropriate, fire doors and compartmentation are complete, affected alarm and suppression systems are restored, and any required testing and commissioning have been completed.
Record outstanding defects and determine whether the affected space can be used safely before it is returned to normal occupancy. Ensure that relevant building records, drawings, system information and maintenance instructions are updated and handed to the appropriate person. In England and Wales, building regulations can also require fire safety information to be provided for specified building work; see Regulation 38 of the Building Regulations 2010 for its scope and requirements.
Finally, review the fire risk assessment and emergency plan against the completed building. The permanent layout, installed fire protection measures and actual use of the premises must align with the arrangements relied upon by building management.
Temporary Fire Safety Checklist for Renovation Projects
Use this checklist as a starting point for planning and site inspections. Adapt it to the project, the fire strategy and applicable local requirements. A completed checklist does not by itself demonstrate that a building is safe; any unanswered item must be assessed and resolved by the appropriate responsible person.
- The renovation scope has been reviewed for fire hazards and changes to the building layout.
- The fire risk assessment has been reviewed by a competent person where needed.
- Roles, authorisation limits and emergency contacts have been agreed.
- Escape routes, exit doors, signage and emergency lighting are suitable for the temporary layout.
- Fire doors, fire-resisting partitions and compartmentation are protected from unnecessary damage.
- Temporary fire detection and warning arrangements are suitable for the affected areas.
- Planned alarm or sprinkler impairments are authorised, recorded and communicated.
- Hot work is assessed, authorised and monitored under the site procedure.
- Suitable firefighting equipment is accessible and designated users know their responsibilities.
- Combustible waste and flammable products are controlled and stored safely.
- Contractors and occupants understand the current evacuation procedure.
- Inspection records, defects and corrective actions are maintained.
- Changes in work activity trigger a review where necessary.
- At the end of work, affected systems are checked and restored, and records are updated.
Example of a temporary control register
| Issue identified | Required action | Responsible role | Verification |
|---|---|---|---|
| Corridor unavailable | Assess alternative escape arrangements and communicate approved changes before closure. | Building manager and site manager | Route inspection and updated instructions |
| Detector affected by dust | Authorise the control method and arrange suitable interim protection where needed. | Authorised fire system representative | Record of isolation, cleaning and restoration |
| Hot work planned | Assess the area, issue the required permit and arrange the specified fire watch. | Permit authoriser and work supervisor | Permit closure and post-work checks |
| Combustible waste accumulating | Remove waste and improve collection frequency or storage controls. | Site supervisor | Housekeeping inspection record |
| Fire-resisting wall opened | Control the opening and provide suitable protection until approved fire stopping is completed. | Project manager and competent fire specialist | Inspection and documented completion |
Each action should have a clear deadline, a named owner and an escalation route if it cannot be completed. Where a control is essential to safe occupancy or work, do not allow the activity to continue on the assumption that the issue will be fixed later.
Common Mistakes to Avoid During Building Renovations
Assuming the existing fire risk assessment is still sufficient
The assessment may no longer reflect the layout, work activities or protection available. Review it when the project changes the risk and document the actions required.
Closing an escape route before an alternative is ready
Do not start by placing barriers across a corridor and deciding later how occupants will leave. Plan, approve and communicate the temporary arrangements first.
Leaving fire alarm devices isolated
Temporary isolation must be controlled and tracked. Assign responsibility for restoration and verification, and escalate any delay that affects safety.
Using a hot-work permit as a substitute for precautions
A signed form does not remove the fire hazard. The work area, combustible materials, hidden voids, suitable equipment and fire watch must be managed in practice.
Failing to tell occupants about changes
People may use familiar routes or misunderstand a temporary alarm arrangement if information is not updated. Communicate changes before they take effect and repeat the briefing when necessary.
Failing to inspect after contractors leave
Conditions can change outside normal working hours. Include suitable end-of-shift checks and arrangements for reporting problems after the site team has departed.
Returning a refurbished area to use too early
Before reoccupation, confirm that the relevant escape routes, fire doors, alarm coverage and other required precautions are suitable. Resolve significant deficiencies before the area is used.
Frequently Asked Questions
What are temporary fire safety arrangements during building renovations?
They are interim measures that protect people and property while building work changes normal fire hazards, escape routes or fire protection systems. They can include revised risk assessments, temporary warning arrangements, hot-work controls, safe material storage and documented system impairment procedures.
Is a fire risk assessment required during renovation work?
Where fire safety legislation applies, the responsible person must meet the applicable risk assessment duties. The assessment should be reviewed when renovation work changes hazards or precautions. The exact legal requirements depend on the premises and jurisdiction.
Can a building remain occupied during renovation work?
Sometimes, but occupancy should continue only where suitable fire precautions can be maintained. Consider escape routes, compartmentation, detection, warning, work hazards and the needs of occupants. If adequate safety cannot be achieved, restrict access, change the work sequence or suspend use of the affected area as appropriate.
What should happen if a fire alarm must be temporarily isolated?
Use the site’s authorised impairment procedure. Assess the effect, obtain approval, notify relevant people, implement suitable interim controls, record the isolation and restore and verify the system as soon as practicable. The affected area may need restrictions if adequate protection cannot be maintained.
What is a hot-work permit?
A hot-work permit is a formal control document used to authorise specified heat- or spark-producing work under defined conditions. It records the hazards, required precautions, responsible people, permitted duration and checks needed before the permit can be closed.
How often should temporary fire safety inspections take place?
There is no single inspection frequency suitable for every project. The schedule should reflect the risk, the rate of change, the type of work and applicable requirements. Inspect more frequently when work conditions, escape routes or protection systems change rapidly or when a higher-risk activity is underway.
Who is responsible for fire safety when contractors are working in an occupied building?
Responsibility can be shared across the building owner, occupier, responsible person, principal contractor and other parties according to their legal duties and control of the premises or work. They should coordinate the building-wide arrangements and clearly allocate responsibilities for the work area and any affected systems.
What should be checked before a renovated area reopens?
Confirm that required escape routes are available, fire doors and compartmentation are suitable, affected alarms and suppression systems have been restored and checked, temporary hazards have been removed or controlled, and relevant records and emergency arrangements have been updated.
Where can I learn more about workplace fire safety?
Start with official guidance from the Health and Safety Executive and the relevant fire safety authority in your jurisdiction. You can also explore the ICTQual Level 3 Award in Fire Safety and the ICTQual Level 2 Award in Importance of Fire Safety pages for information about relevant learning options.
Conclusion: Plan for Fire Safety Throughout the Renovation
Temporary fire safety arrangements during building renovations must evolve with the work. A building that was safe before construction began may present different risks once partitions are removed, escape routes change, hot work starts or fire protection systems are affected.
The most effective approach combines a current fire risk assessment, clear responsibilities, safe escape routes, suitable warning arrangements, strict ignition control, good housekeeping and a formal process for managing system impairments. Regular inspections and clear communication help ensure that temporary precautions remain effective as the project progresses.
Before work starts, establish who is responsible for each control, how it will be checked and what happens if it fails. Before the building returns to normal use, verify that the necessary protection has been restored and the final arrangements reflect the completed premises.
Build Your Fire Safety Knowledge
Develop your understanding of fire prevention, workplace precautions and risk management with relevant fire safety learning resources.
Official Guidance and Further Reading
The following resources support the practical guidance in this article. Check the latest version and confirm which requirements apply to your premises.
- Health and Safety Executive: General fire safety in construction — construction fire risks, escape, warning and firefighting arrangements.
- GOV.UK: Fire safety risk assessment five-step checklist — a framework for identifying hazards, protecting people, planning and review.
- GOV.UK: Who is responsible for workplace fire safety? — responsible persons and coordination between dutyholders.
- The Building Regulations 2010, Regulation 38 — fire safety information for specified building work.
- International Code Council: Fire safety during construction and demolition — an additional technical reference; confirm whether this code is applicable in your jurisdiction.
Disclaimer: This article provides general educational information and is not a substitute for a site-specific fire risk assessment, competent professional advice or applicable legal requirements. The examples are not a complete list of precautions. Requirements vary by building type, occupancy, work activity and jurisdiction. Verify current requirements with the relevant authority and competent fire safety professionals before implementing temporary arrangements.